A, B and C can complete a pice of work in 24, 6 and 12 days respectively. Working together, they will be complete the same work in:
A, B and C can complete a pice of work in 24, 6 and 12 days respectively. Working together, they will be complete the same work in:
- ক. 1/24 days
- খ. 7/24 days
- গ. 24/7 days
- ঘ. 4 days
সঠিক উত্তরঃ 24/7 days
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- If it takes 50 workers 4 hours to dig a hole, how long should it take 30 workers to dig the same hole?
- A time study specialist has set the production rate for each worker on a job at 22 units every therre hours. At this rate, what is the minimum number of workers that should be put on the job, if at least 90 units are to be produced per hour?
- If 5 men and 9 women can do a pice of work in 19 days, then in how many days will 3 men and 6 women do the same work?
- A and B together can paint a wall in 3 days. A can do it alone in 5 days. How many days would it take B to do this job alone?
- Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?
There are no comments yet.