A and B together can paint a wall in 3 days. A can do it alone in 5 days. How many days would it take B to do this job alone?
A and B together can paint a wall in 3 days. A can do it alone in 5 days. How many days would it take B to do this job alone?
- ক. 0.5
- খ. 7.5
- গ. 5.0
- ঘ. 6.4
সঠিক উত্তরঃ 7.5
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?
- Ram can do a job in 20 days while Sham can do the same job in 25 days. After working for 10 days together, Sham left and Ram finished the job. How many days did Ram take to finish the job?
- A and B can do a work in 12 days. B and C can do it is 15 days and A and C can do it in 20 days. If all of them work together, in how many days they can finish the work?
- An empty pool is being filled with water at a constant rate. It takes 9 hours to fill 3/5 th of the pool. How much more time will it take to compeletely fill the pool?
- A man and a boy can finish a job working together for 4 days. The man can work as much as two boys can do. Then in how many days can the man do it alone?
There are no comments yet.