Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?

গণিত Time and Work 07 Oct, 2020

প্রশ্ন Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?

  • ক.
    7 days
  • খ.
    6 days
  • গ.
    8 days
  • ঘ.
    24/7 days

সঠিক উত্তর

24/7 days