সকল সরকারী/বেসরকারী পরীক্ষার প্রশ্ন পেতে ক্লিক করুন গণিতের আইকিউ টেস্ট করতে ক্লিক করুন
A contractor employs 60 person for doing a job in 80 days. After 20 days it was found that only one-fifth of work was finished.How many more persons are to be employed to finish the job as per schedule?
A contractor employs 60 person for doing a job in 80 days. After 20 days it was found that only one-fifth of work was finished.How many more persons are to be employed to finish the job as per schedule?
- ক. 20
- খ. 80
- গ. 60
- ঘ. 40
সঠিক উত্তরঃ 20
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- If 6 workers can complete 9 identical job in 3 days, how long (in days) will it take 4 workers to complete 10 such jobs?
- A television service centre can process 8 television in 18 minutes. How many televisions can it process in 3 houres at this rate?
- Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?
- A contractor employs 60 person for doing a job in 80 days. After 20 days it was found that only one-fifth of work was finished.How many more persons are to be employed to finish the job as per schedule?
- Mr. Shahin moved 3/4 th of his lawn in 5/4 hours. Mr. Ashique makes twice as fast and finishes the remaining job. How many minutes did Mr. Ashique work?
There are no comments yet.