সকল সরকারী/বেসরকারী পরীক্ষার প্রশ্ন পেতে ক্লিক করুন গণিতের আইকিউ টেস্ট করতে ক্লিক করুন
A contractor employs 60 person for doing a job in 80 days. After 20 days it was found that only one-fifth of work was finished.How many more persons are to be employed to finish the job as per schedule?
A contractor employs 60 person for doing a job in 80 days. After 20 days it was found that only one-fifth of work was finished.How many more persons are to be employed to finish the job as per schedule?
- ক. 20
- খ. 80
- গ. 60
- ঘ. 40
সঠিক উত্তরঃ 20
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- A and B can do a work in 12 days. B and C can do it is 15 days and A and C can do it in 20 days. If all of them work together, in how many days they can finish the work?
- A cake is put in the oven at 7.20 am. If the cake takes three quarters of an hour to bake, at what time should it be taken out of the oven?
- A machine produces 1000 units of plastic chair per hour. Working continuously at this rate how many plastic chair will this machine produce in a week?
- Three pipes are used to fill a pool with water. Individually they can fill the pool in 9 hours, 6 hours and 3 hours. How many minutes will it take to fill the pool if three pipes are used simultaneously?
- Six men can complete a work in 5 days if they work for 8 hours per day. How many days will 4 men take to do the same work if they work only 5 hours per day?
There are no comments yet.