If 8 men can do a job in 12 days, what is the percentage increase in the number of days required to do the job when 2 men are released?
If 8 men can do a job in 12 days, what is the percentage increase in the number of days required to do the job when 2 men are released?
- ক. 33.33%
- খ. 20%
- গ. 4%
- ঘ. 25%
সঠিক উত্তরঃ 33.33%
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- Mr. Shahin moved 3/4 th of his lawn in 5/4 hours. Mr. Ashique makes twice as fast and finishes the remaining job. How many minutes did Mr. Ashique work?
- Ram can do a job in 20 days while Sham can do the same job in 25 days. After working for 10 days together, Sham left and Ram finished the job. How many days did Ram take to finish the job?
- Nazir can wash his car 15 minures while his son takes twice as long. If they work together how many minutes will the job take them?
- A mechanic repairs 4 cars in 5/3 hours. How many cars can he repair in 50 minutes?
- K produces 100 parts twice as fast as G does. G produces 100 parts in 40 minutes. If each produces parts at a constant rate, how many parts will K produces in 6 minutes?
There are no comments yet.