If 8 men can do a job in 12 days, what is the percentage increase in the number of days required to do the job when 2 men are released?
If 8 men can do a job in 12 days, what is the percentage increase in the number of days required to do the job when 2 men are released?
- ক. 33.33%
- খ. 20%
- গ. 4%
- ঘ. 25%
সঠিক উত্তরঃ 33.33%
এ সম্পর্কিত আরো প্রশ্ন দেখুন
- A television service centre can process 8 television in 18 minutes. How many televisions can it process in 3 houres at this rate?
- Faruk can complete a task in 20 days. He gets 2 assistants- each of whome can work as fast as he does. If all of them work together for 5 days, what percentage of the task will be complete?
- 20 men can finish a work in 30 days. After how many days should 5 men leave the work so that the work may be finished in 35 days?
- Six men can complete a work in 5 days if they work for 8 hours per day. How many days will 4 men take to do the same work if they work only 5 hours per day?
- A machine produces 1000 units of plastic chair per hour. Working continuously at this rate how many plastic chair will this machine produce in a week?
There are no comments yet.