There would be exactly one order in which the four projects would have to be started if it was determined that--
There would be exactly one order in which the four projects would have to be started if it was determined that--
- ক. F has priority over H
- খ. F has priority over I
- গ. H has priority over G
- ঘ. I has priority over F
সঠিক উত্তরঃ I has priority over F