Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?

গণিত
Time and Work

প্রশ্নঃ Mr. X can finish a work in 6 days and Mr. Y can finish the same work in 8 days. How long will it take to finish the work together?

  • ক. 7 days
  • খ. 6 days
  • গ. 8 days
  • ঘ. 24/7 days

সঠিক উত্তরঃ

24/7 days